07-29-2022Church Building Update

The rebar is being installed for the south transept, the north restrooms, the elevator shaft area and the back of the new Sanctuary. The block is scheduled to arrive on Friday. Footings to be completed by Monday, concrete to be poured starting Tuesday, mason is scheduled to start on Wednesday, and the catch basin for the east drain is scheduled to arrive on August 6th.

As we were in our construction meeting, a heavy rain storm hit St. Benedict. The footing trenches had 3 feet of water in them. This could impact the above schedule. The footings will need to be inspected prior to the concrete being poured.