09-09-2022Church Building Update

The ABC stone will be spread next week in preparation for pouring of the slabs. Concrete has been ordered for next Wednesday for pouring the slabs. Workers will be saw-cutting the east and west walls for the i-beams that will support the loft. The choir loft decking is 4 to 6 weeks out which may impact the pouring of the west slab. We need to allow the heavy equipment access to construct the loft infrastructure. The masonry on the north and south side of the buildings will commence after the slabs are poured. We will see the walls starting to go up.

This week's photos:

  • The Sacristies
  • The Sanctuary work is waiting for choir loft steel
  • The ABC stone is delivered