The framers and iron workers continue to work on the bell tower roof. The target for framing to be completed is the end of this week. The roof decking should arrive by Friday, this week. The concrete framing for the east and northeast sidewalks has been delayed due to the weather. As soon as it dries out, this work can continue. The mechanical team is doing a great job. The A/C mechanical work is approximately 80% complete. The electrical rough-in has begun.
Scheduled this week (weather permitting): east and northeast sidewalks poured; decking installed on tower roof; decking installed on south transept; begin framing inside Chapel; erecting the scaffolding for the stucco work; developing schedule for grading of the property; work continuing for framers, plumbers, electrical and mechanical.