The rain impacted the installation of the stem walls. We anticipate the stem walls to be completed by Tuesday. The underground plumbing should be installed next week, depending on the weather. The underground electrical is scheduled for the following week, also depending on the weather.
The storm drainage solution going under the driveway between the main building and the Annex buildings did not hit the targeted plan of being completed prior to the start of school. This was due to supply chain delays. The material is now in. As not to impact the school's car pool lanes, this work will be done during the Christmas break, starting Dec 19.