Framing and the A/C duct work continues to progress. Decking has begun to be installed, starting with the bell tower then proceeding to the southside of the building. The team will continue to work around the building. A ladder, which is the only access to the upper roof, has been installed. The power to the 2 future monument signs have been installed, one by the south entry drive and one by the north entry drive.